ITCertKing could give you the Microsoft 70-178 exam questions and answers that with the highest quality. With the material you can successed step by step. ITCertKing's Microsoft 70-178 exam training materials are absolutely give you a true environment of the test preparation. Our material is highly targeted, just as tailor-made for you. With it you will become a powerful IT experts. ITCertKing's Microsoft 70-178 exam training materials will be most suitable for you. Quickly registered ITCertKing website please, I believe that you will have a windfall.
ITCertKing is the only website which is able to supply all your needed information about Microsoft certification 70-178 exam. Using The information provided by ITCertKing to pass Microsoft certification 70-178 exam is not a problem, and you can pass the exam with high scores.
Exam Code: 70-178
Exam Name: Microsoft (Microsoft Project 2010, Managing Projects)
One year free update, No help, Full refund!
Total Q&A: 70 Questions and Answers
Last Update: 2013-10-09
If you attend Microsoft certification 70-178 exams, your choosing ITCertKing is to choose success! I wish you good luck.
ITCertKing's expert team has developed a latest short-term effective training scheme for Microsoft certification 70-178 exam, which is a 20 hours of training for the candidates of Microsoft certification 70-178 exam. After training they can not only quickly master a lot of knowledge, but also consolidate their original knowledge. So they can easily pass Microsoft certification 70-178 exam and it is much more cost-effective for them than those who spend a lot of time and energy to prepare for the examination.
70-178 Free Demo Download: http://www.itcertking.com/70-178_exam.html
NO.1 You manage several projects. Each project has shared resources and work distribution. You need to
ensure that you can adjust the workload for specific resources used across multiple project schedules.
What should you do?
A. Enable the Load Summary Resource Assignments option. Then, select the Level Resource function on
each project.
B. Open the individual schedules and use the Visual Reports option. Then, use the Resource Usage view
to manually modify resource Work.
C. Open a blank project and select Insert Subproject for each project schedule. Then, use the Level
Resource function for selected resources.
D. Open the shared Resource Pool for each project schedule. Then, use the Level Resources function.
Answer: C
Microsoft 70-178 70-178 certification 70-178 original questions
NO.2 You use bottom-up scheduling. You need to group four consecutive tasks in a major phase. You
highlight the four tasks. Which command should you use?
A. Outdent
B. Fill Down
C. Insert Summary
D. Move Task
Answer: C
Microsoft pdf 70-178 70-178 70-178 original questions 70-178 70-178 braindump
NO.3 You manage a project that specifies all constraint types to As Soon As Possible. You discover that one
of your key tasks is scheduled to end prior to the targeted finish date. You need to display the targeted
finish date on the default Gantt chart. What should you modify in the Task Information window?
A. Set the Deadline date field.
B. Set the Constraint date field.
C. Set the Finish date field.
D. Select the Mark task as milestone check box.
E. Select the Display on Timeline check box.
Answer: A
Microsoft dumps 70-178 test questions 70-178 practice test
NO.4 You need to view Task ID 0 on your project plan. What should you do?
A. On the Advanced tab of the Project 2010 options, select Show Status Bar.
B. On the Format tab, select Summary Tasks.
C. On the Format tab, select Project Summary Task.
D. Insert a new Summary Task.
Answer: C
Microsoft test answers 70-178 answers real questions 70-178 exam dumps
NO.5 You have a Project 2010 schedule that contains the following tasks:
Inactive tasks
Manually scheduled tasks
Manually scheduled summary tasks
Tasks that contain strikethrough font
You want to save the schedule as a Project 2007 project. You need to ensure that no new milestones are
created. What should you do.?
A. Change all inactive tasks to active tasks.
B. Change all tasks that contain strikethrough font to tasks that include normal font.
C. Change all manually scheduled summary tasks to automatic scheduling.
D. Change all manually scheduled tasks to automatic scheduling.
Answer: C
Microsoft 70-178 pdf 70-178 practice test 70-178 70-178 70-178 pdf
NO.6 You need to set the default constraint type for all new tasks to As Late As Possible. What should you
do?
A. Select all tasks, and then click Layout.
B. In the Options dialog box, enable the New Tasks are effort driven check box.
C. Select all tasks, and then set the constraint type to As Late As Possible.
D. In the Project Information window, from the Schedule From drop-down list box, select Project Finish
Date.
Answer: D
Microsoft exam dumps 70-178 70-178 practice test 70-178 dumps
NO.7 The project you manage has only part-time resources. The part-time resources work four hours a day
from Wednesday through Saturday. You need to create a new calendar and set the calendar as the
default for your project. Which two actions should you perform? Each correct answer presents part of the
solution.
A. Select the part-time calendar from the Change Working Time window.
B. Set the calendar type to part-time for all tasks.
C. Select the part-time calendar from the Project Information window.
D. On the Project tab, Select Change Working Time, and then click Create New Calendar.
E. Change the Calendar type in the Project Options dialog box.
Answer: CD
Microsoft 70-178 70-178 70-178 70-178
NO.8 You manage a project according to the schedule as shown in the exhibit.
You need to set the Task Mode for task 4 to be the same as task 6. What should you do?
A. Create a task dependency from Task 4 to Task 6.
B. Set Task 4 as critical.
C. Add a 1 day lead to Task 4.
D. Set Task 4 as manually scheduled.
Answer: D
Microsoft 70-178 70-178 questions 70-178 70-178
NO.9 The first major phase of your project is scheduled for a duration of 45 days. However, you do not have
task information for other phases. You need to indicate that the duration of the entire project is 200 days.
What should you do?
A. Select the Project Summary Task option.
B. Select the Summary Tasks option.
C. Create a manually scheduled summary task.
D. Update the project calendar.
Answer: C
Microsoft exam dumps 70-178 70-178 70-178 70-178 braindump
NO.10 A section of your project contains only a summary task along with four subtasks and a milestone. You
discover that the section is located in the incorrect phase and has the incorrect Work Breakdown
Structure (WBS) numbering. You need to move the section to another phase of the project. You also need
to ensure that the section reflects the correct WBS numbering. What should you do?
A. Select the summary task and change the scheduling mode to Manually Scheduled.
B. Select the entire section and click Move Task.
C. Drag the summary task.
D. Modify the start and finish dates of the summary task.
Answer: C
Microsoft exam 70-178 70-178 exam 70-178 exam simulations
ITCertKing offer the latest 100-101 exam material and high-quality 70-331 pdf questions & answers. Our CAT-221 VCE testing engine and C_TFIN52_64 study guide can help you pass the real exam. High-quality 1Z0-033 dumps training materials can 100% guarantee you pass the exam faster and easier. Pass the exam to obtain certification is so simple.